- Owner: SCDOT Construction
- Cost: $3,530,000
- Completion Date: October 2014
Scope of Services:
- Design Build Project
- Single span BT54 girder bridge
- Pile supported end bents
- Concrete slope protection
- ROW, Slope Permissions, Permitting
- Earthen embankments and bridge approaches, consisting of approx.. 35,000cy of borrow excavation, approx.. 4000 tons of asphalt
- Concrete parapet walls and approx. 2000lf of guardrail
- Traffic Control and Erosion Control